This project consisted of multiple modifications to an existing high pressure 16in natural gas line to properly run a smart pig. PLE crews installed 4 – 16” x 20” pig launchers/receivers, 9 – 16” Main Line Valves, and 7 – 16” Tees over a 75 miles section of the pipeline. This project utilized numerous line- stops throughout the construction process. PLE utilized their skilled crews to complete all facets of the project which included the civil, mechanical, and electrical installations.