Mullinville, KS – 24in Pipeline Emergency Installation

This project consisted of the emergency installation of a 24in pipeline via Conventional Bore beneath an existing Railroad Track.  The project consisted of a 130 LF Conventional Bore beneath an active Railroad Track with the requirement of a single 24-inch line stop. ...

Delanson, NY – Filter Separator Upgrade

This project included the installation of a new 73,000 lb. filter separator, fabrication and pressure testing of 2”, 24” and 30” piping, valves, and drain/storage tank. PLE also fabricated and installed all platforms, railings, and stairs to ASME/ASTM standards. The...

Portland, ME – Jack and Bore Replacement

This project implemented the use of a jack and bore method to install 200’ of 16” casing and 8” carrier pipe under I-95, with an additional 400’ of 8” running parallel to the highway. The entry and exit pits, were 20 – 25’ deep, required the use of engineered approved...